Walking routes: plans and progress
The Tawd Valley Park is a beautiful valley to walk in. The Masterplan features significant improvement works to the existing footpaths that will make it even more enjoyable and accessible for all.
The footpath improvements are among the first works scheduled and started in May 2019 in the Northern Zone (above Summer St). Paths shown in red below will be upgraded, with work due to be completed in summer 2019.
Schedule of footpath improvements in all zones:
Northern zone: start – Spring 2019, completion – Summer 2019
Central zone: works start 2020
Town centre zone: works start Autumn 2019